The monastic silence of Saint-Maurice has been temporarily disturbed over the last few weeks by the arrival of heavy railway equipment.
This is already our 5th project as part of the BM3 project (Bauen mit Dritten) in 2023 on behalf of SBB CFF FFS. 7 turnouts and 180 m of track connections were renewed. In addition, 40 m of infrastructure was treated under a double turnout.
The work carried out, among other things, on a main track at the entrance to the St-Maurice Tunnel demanded the highest safety standards.
The replacement of the switches and crossings was carried out in 2 "Coup de Poing" operations lasting 56 hours over 2 weekends in July. Finishing work was spread over the following weeks.
GESTE Engineering acted as Local Works Management and Assistance to the General Works Management, acting as intermediary between the project owner and the works contractor - Rhomberg Sersa Rail Group.
A big thank you to all the people involved in this project!
2023